The MA DOT will commence with the resurfacing of Still River Road (Route 110) on Thursday evening (4/21). The initial work includes the milling of the existing roadway pavement to prepare for the new road surface. Work is expected to begin at the Harvard line and proceed southerly toward Lancaster. The work will occur between the hours of 7PM and 5AM. While this milling is ongoing, traffic will be impacted in the work zone.
The Contractor will be working overnights Thursday/Friday, Sunday/Monday, and Monday/Tuesday. The section of roadway in Bolton is expected to take 3-4 days.
Paving of the roadway is expected to occur in mid May. Additional notices and advisories will be posted once that date is known.
Original source can be found here.